Project: WMC – Maria Fareri Hospital
Location: Valhalla, New York
HVAC Contractor: AMX
Project Duration: July 02 to December 04
Contract Value: $13,600,000.00
Project Scope:

Three 500 Ton Chillers

3-Cell Cooling Tower

Ten Pumps

CHW, CW, HW, GHW & Steam Systems

Twelve Large AHU’s

Forty-Seven Fan Systems


Three Hundred VAV & CV Boxes

Five Split AC Systems

High, Medium & Low Pressure Steam

Fuel Oil System – Emergency Generator
Project Responsibilities:

Sheetmetal

HVAC Piping

HVAC Insulation

HVAC Controls

Air & Water Balancing

System Start-Up & Testing